For additional information about this project, please contact Associate Civil Engineer Craig Murray at craig.murray@chicoca.gov or (530) 879-6931

State Route 32 Widening Project (Phase 2)

The work, in general, to be done under this contract consists of installation of new traffic signals at the Fir Street intersections with State Route 32; modification of existing traffic signals at the State Route 99 on and off ramps; installation of a Class I bike path and a Class II bike lane along Fir Street; installation of curbs, gutters, sidewalks, curb ramps and landscaping; and modifications to the existing transit and Park and Ride facilities.

Some of these files are large and may take time to download. Please be patient.

PLANS AND SPECIFICATIONS

SR32 P2 Bid Book

SR32 P2 Bid Plans

SUPPLEMENTAL INFORMATION

SR32 P2 Supplemental Information-1 Geotechnical Design Report (GDR)

SR32 P2 Supplemental Information-2 Materials Report

SR32 P2 Supplemental Information-3 As Builts

ADDENDUM 1

SR32 P2 Addendum 1 - Cover Sheet

SR32 P2 Addendum 1 - Plans

SR32 P2 Addendum 1 - Supplemental Information-4 General Cross Sections

ADDENDUM 2

SR32 P2 Addendum 2 - Cover Sheet

SR32 P2 Addendum 2 - Revised Federal Prevailing Wage Rates

SR32 P2 Addendum 2 - Supplemental Information-5 NOI Backup Data

ADDENDUM 3

SR32 P2 Addendum 3 - Cover Sheet

SR32 P2 Addendum 3 - Specifications

ADDENDUM 4

SR32 P2 Addendum 4 - Cover Sheet